Marc & Jean-Sébastien WILDCAT page

29 May 2004

Already two months of building.



Including one night ( Epoxy sealer application ) + one or two late evenings.



31 May 2004



July 7th From June 1st to Mid July...
We probably worked a total of 15 hours...



27 July 2004



6 August 2004

Web stiffeners are being installed.





21 August 2004

FINALLY... We're finally ready to plank!





22 August 2004



27 August 2004



8 September 2004



22 September 2004



24 September 2004

This shows a "batten" from transom to "Aft" bulkhead... Not in plans.



This picture shows a transom knee. Not in the Wildcat plans but is on BearCat study plans.



30 September 2004

How can you punch a hole through your finger?
Just hammer a sharp drill bit!





7 October 2004

The hull is sealed.



8 October 2004

This is what a scarf joint looks like.


Continue