October 26,03
Thanks to a Humidity & Temperature Gauge, without it, the painting work
would be by guessing only. Doing the painting work during the early Monsoon
Shower is full of suspense & fun. Sometimes we have to act as a local
weather forecaster. Can not entirely depend on TV & Radio Forecasting, not
accurate enough. Choosing EPIFANES System is a right decision, their standing
time after mixing (polyurethane) is longer (8 hours) before reaching cure time
or hardened.
Epifanes Two-Component paint system on Fiberglass below waterline with
Osmosis Prevention consists of: 1 coat of Epifanes Interimcoat, 5 coats of
Epifanes Epoxy Coating HS, 1 coats of Interimcoat and 3 coats of Epifanes
Foul-Away.
Two Component paint system on Fiberglass above the Waterline. 1 coat of
Epifanes Epoxy Primer and 3 coats of Epifanes Polyurethane.
November 03, 03
At 0700 hours made a final inspection from the Check List. Dismantling work
shelter ...done. Dismantling roof in between 2 cabins ...done. Crane and
operator at site ...done. General briefing to the crane's operator of
method of lifting and Safety briefing ...done. Alright! Let's do it!