      Fig 36: The hull is righted and chocked level to prevent
      distortion while the deck and interior is completed.
      
      
     
       
      
     
      Fig 37: The intermediate deck beam is arced to the same crown as
      the Frame 5 deck beam. Note the blocking for this member at the sheer.
      
      
     
       
      
     
      Fig 38: The carlings are sprung into position and glued and
      fastened at the transom, each of the frames and the Frame 5 beam.
      
      
     
       
      
     
      Fig 39: Trimming the planking and beveling the sheer for the
      decking must be done carefully to provide a fair surface to attach decking
      to.
      
      
     
       
      
     
      Fig 40: The athwartship 2" x 4" (nominal) member is
      beveled to mate to the transom, glued and fastened in place.
      
      
     
     |